In line with the 14 megaproject to reduce the imbalance of production and consumption in the summer of 1404; The Khorramabad 7 mobile superdistribution power station was put into operation
- January 5, 2025
- 10:42 am
- News
- No Comments
- 3 views
In line with the 14 megaproject to reduce the imbalance of production and consumption in the summer of 1404;
The Khorramabad 7 mobile superdistribution power station was put into operation
The supervisor of the transmission and superdistribution substations of Lorestan province said: In line with the 14 megaproject to reduce the imbalance of production and consumption of electricity in the summer of 1404, by carrying out construction, transportation, installation, testing and commissioning of the project equipment, the Khorramabad 7 mobile substation was constructed and electrified in Lorestan province.
According to the public relations report of the Bakhtar Regional Electricity Company, “Mohammad Azdi” while stating the above news added: The aforementioned 20 kV 63 power station was constructed in order to provide stable and reliable electricity to a part of the northern part of Khorramabad city in the center of Lorestan province.
He stated: The station with a capacity of 30 megavolts, along with a 63 kilovolt mobile substation and a 30 megavolts transformer with a capacity of 20 kilovolts, along with a 6 kilovolt mobile switchgear with 6 output feeders, was put into operation and electrified.
Azadi continued: With the launch of the station, in addition to increasing the reliability of the region, the necessary infrastructure was also provided for the development of the national housing of this city in the future.
He concluded by saying: The station was put into operation with a credit of 700 billion rials.
He added that this project is one of the projects to develop and remove restrictions from the country’s electricity networks, which is under the management of the Bakhtar Regional Electricity Company in Lorestan province.
It should be noted that the Bakhtar Regional Electricity Company is responsible for transmitting electrical energy in the three central provinces, Hamadan and Lorestan.